Jokeri Light Rail contact lines installed in March
Construction of the Jokeri Light Rail system is nearing completion in Otaniemi. Currently on winter break, work will resume in March with installation of contact lines between Maarintie and Otaniementie.

Work this week (Week 9) begins with snow removal. Contact line installations will start during Week 10 and include setting electrical cross-arms and stringing overhead cables. Construction will occur on day shifts and on night shifts, depending on the work phase. Caution should be exercised when near the work area as heavy machinery and equipment will be moving along the tracks from Maarintie all the way to Otaniementie. The work will not result in significant noise.
The contact line work is scheduled to last until Week 13.
Additional information
Text: Jokeri Light Rail
Read more news

Glitch artwork challenges to see art in a different light
Laura Könönen's sculpture was unveiled on 14 October at the Otaniemi campus.
The research puzzle of when humans and AI don’t see eye to eye
Francesco Croce works on robustness in multi-modal foundation models
The certificate for aalto and eduroam networks changes on 14 October 2025
Users may receive a notification or a confirmation request on the change of the certificate